Issues List

+ New Issue

Active Issues

ID Title Opened Updated Description Priority Status Status Detail Action
6 Flooring 2025-12-27 2026-01-17 Incorrect floor color was substituted without customer consent 1 Advised Hal on Dec 27 that material didn't match expectations or description from selection sheet Advised by Hal on Dec 29 that product we selected was discontinued and substituted without notice/consent Escalated to Derek by Hal, and agreed that material was to be consolidated from remaining stock at Hayden, Summertown, and Morristown. Old floor removed 18Jan New floor 800sf installed 18Jan Edit
2 Ceiling in 4th Bedroom 2026-01-08 2026-01-17 Ceiling has a crease visible at the transition from cathedral to flat 2 Advised Jeff - Jan 08 To be remediated during paint/drywall Edit
3 Stove vent electrical 2026-01-08 2026-01-17 Electric outlet for stove vent is not connected to a breaker 3 Open Advised Jeff - Jan 08 Edit
4 Second Bath Outlet 2026-01-08 2026-01-17 Outlet over right basin will be blocking/blocked by mirror, needs to be moved to right 3 Open Advised Jeff - Jan 08 Edit
13 Doors 2026-01-17 2026-01-17 interior doors 3 Installation pending Material received and staged in garage Edit
23 Damage - Kitchen Cabinet 2026-01-17 2026-01-17 Lower corner on cabinet closest to refrigerator has damage 3 Open Edit
22 Damage - Stove Vent 2026-01-17 2026-01-17 Lower corner of stove vent has damaged wood due to handling 3 Open Edit
21 Lighting over island 2026-01-17 2026-01-17 Holes for pendant lights are not cut 3 Installation pending Per Hal, this will be done after island is installed Edit
20 Lighting over sink 2026-01-17 2026-01-17 No hole or outlet for oversink light 3 Installation pending Per Hal, this will be done after sink installation Edit
19 Electric Supply Riser 2026-01-17 2026-01-17 Riser at the external house disconnect is Sch 40, but Sch 80 is required from ground to 5ft per local electrician. 3 Inspection pending This has not failed inspection yet, but could hold up final electrical inspection if the local inspector flags it as an issue. Edit
18 Kitchen Backsplash 2026-01-17 2026-01-17 Upgraded backsplash for kitchen 3 Installation Pending Material staged on back porch Edit
17 Bath Tile 2026-01-17 2026-01-17 Upgraded tile form master bathroom including tile floor 3 Installation Pending Material staged on back porch (tile) Material list for installation received Jan 08 Edit
15 Water 2026-01-17 2026-01-17 Water installation 3 Installation Pending Advised Hal on Dec 28 that supply line is buried and ready for plumber to connect. Shut-off valve in vault located 30-40 feet off front porch (shop side) Edit
14 Trim 2026-01-17 2026-01-17 Trim wood in 4 and 6" widths 3 Installation pending Material staged in garage Edit
11 Microwave circuit 2026-01-17 2026-01-17 Microwave circuit was not installed to island location 3 Open Circuit rerouted to junction box behind leftmost cabinet, and whip installed thru floor chase. Electrician will need to splice and wire outlet Edit
10 Door orientation - Pantry 2026-01-17 2026-01-17 Door to pantry is to swing outward into kitchen 3 Open Hal advised on walk thru - November 13 Edit
9 Door Orientation - hallway 2026-01-17 2026-01-17 Door from main room is to swing into hallway 3 Open Hal advised on walk thru - November 13 Edit
8 T&G Installation 2026-01-17 2026-01-17 Installation of tongue and groove ceiling 3 Installation pending Wood prepared by customer and staged in shop Advised Jan 18 by installer that drywall should not have been installed where T&G was going, and that electrician would need to drop existing boxes. Edit
7 Rock Order 2026-01-17 2026-01-17 Custom order from Centurian: Sillohuette Catalina 3 Delivery Pending Advised Shelby and Hal of rock selection on November 13 -- Centurion Rock, Silhouette - Catalina which has a longer lead time Order confirmed by Jeff Edit
1 Stove vent opening 2026-01-08 2026-01-21 Vent is about 12" off center and visible when vent hood cabinetry is in place 4 Advised Jeff - Jan 08 Jeff adjusted location and left open for drywall crew to address - 21Jan Edit
24 Disposal Switch 2026-01-21 2026-01-21 No provision for a garbage disposal switch near kitchen sink 4 Open Advised Hal, said he would pass along to electrician. Outlet already provided under sink, so this just needs the outlet to be wired into a switch. Edit
Closed Issues
5 Chimney Leak into Attic Leak identified at base of chimney and roofline Resolved Identified to Hal in November Observed wet insulation on Jan 05 (chimney installer) Not observed by STM personnel on Jan 08 Not observed by Jeff on Jan 15 Edit
12 Countertops - Kitchen Wrong material delivered Closed Correct material installed on 05 Jan, incorrect sent for pantry, however specification sheet did not have any mention of the pantry or laundry. Accepted incorrect material to avoid further delay Edit
16 Attic decking Attic deck by HVAC was not completed with two 4x8 sheets Open Advised by Shelby on Oct 13 that two sheets should have been provisioned for the mechanical space. HVAC installers used a large scrap to position the HVAC equipment, but no decking is available for safe access to inspect or perform maintenance. Closed Jan 14 as this isn't contractual. Edit